Thank you for sharing your concerns regarding traffic signal operations during the Speedvale Avenue bridge construction/ closure.
In anticipation of changes in travel patterns resulting from the closure, City Traffic Signal staff implemented enhanced signal timing plans along the designated detour routes. These improvements were programmed on Woolwich Street, Woodlawn Road East, and Victoria Road, as a significant number of vehicles were expected to use these corridors to travel between Victoria Road and Woolwich Street.
Since the partial bridge closure, staff have also observed increased traffic volumes travelling southbound on Woolwich Street toward Eramosa Road. In response, staff conducted field observations and made signal timing adjustments at key intersections to better accommodate the increased demand.
Southbound Delays at Woolwich Street and Eramosa Road/Wyndham Street:
During the afternoon peak period, significant delays occur for southbound traffic on Woolwich Street. These delays are primarily the result of increased demand for the southbound left-turn movement from Woolwich Street onto Eramosa Road.
To address this, signal timing for the southbound left-turn phase has been extended to the maximum practical duration. Currently, a minimum of 16 vehicles can complete the left turn during each protected green arrow phase. Despite these adjustments, delays continue due to the high traffic volumes on all approaches to the intersection. As a result, there is no additional green time available that can be assigned to the southbound left-turn movement without causing significant impacts to other traffic movements.
Woolwich Street at Norwich Street / Norfolk Street:
During peak travel periods, traffic delays on Woolwich Street are also influenced by increased volumes travelling southbound and the substantial number of vehicles turning left at Wyndham Street. As a result, even with the provision of a protected southbound left-turn signal, vehicles are often unable to clear the intersection during a signal arrows.
City staff will continue to monitor traffic operations and signal performance along the detour routes and will make further timing adjustments where operationally feasible to improve traffic flow while balancing the needs of all road users.
Thank you for your feedback and patience during the bridge closure.
Traffic going to Eramosa bridge due to Speedvale construction
From "Speedvale Avenue East Reconstruction Phase 2 - Bridge Replacement Q&A"
Go to the project
Would it be possible to study the traffic at the lights from southbound Woolwich St at the 5 corners to the lights at Eramosa. People who need to go eastbound on Speedvale can only use Eramosa Rd or Woodlawn eastbound. At different times of day, the advance left turn at Woolwich southbound at five corners turns green but cars cannot turn because the traffic is backed up. Would someone please gather the traffic data and configure the lights so that the traffic flows?
Official updates
Last update: July 13, 2026
Posted on July 13, 2026
Comments
Please to comment.
Total likes: 0, total dislikes: 0
. Sign in to react.
Share
Posted by
Current status
answered