College Avenue infrastructure upgrades

About the project

The City of Guelph is working to replace and upgrade water and wastewater infrastructure, and design and construct protected cycling infrastructure on College Avenue from Janefield Avenue to Dundas Lane. The 2.75 kilometre corridor will feature cycle tracks between Edinburgh Road and Gordon Street, and protected bike lanes from Janefield Avenue to Edinburgh Road and from Gordon Street to Dundas Lane.

Four intersections will be upgraded to become protected intersections: Scottsdale Drive, Edinburgh Road, Gordon Street and East Ring Road. Protected intersections divide motor vehicles, cyclists and pedestrians into separated paths to navigate the intersection, providing safe passage for each group with minimal conflict points.

Map of the construction area:

Construction phase map with Phase 1: Edinburgh to University (complete), Phase 2: University to Gordon (2025 – 2026) Phase 3: Janefield to Edinburgh and Gordon to Dundas Lane (2027)

How to Participate

Our engagement concluded on this project in 2023. While we are not asking for feedback about this project, we are moving forward with construction and we do want to keep you informed. More information on the College Avenue infrastructure upgrades Guelph.ca page.

If you have questions about the project or the construction we want you to be able to ask them and to get answers. Reach out to the project managers under the "Who's Listening" column with any questions.

Please note: This project began in an older version of our website. Some of the tools and information may appear different than originally designed.

Who's Listening

headshot of Kate Berry

Kate Berry, Project Manager, Sustainable Transportation

Kate.berry@guelph.ca

Benita van Miltenburg

Benita van Miltenburg, Project Manager Sustainable Transportation

Benita.VanMiltenburg@guelph.ca

Black and white headshot of Pacifique Nicholas

Pacifique Nicholas, Project Engineer, Engineering & Transportation Services

Pacifique.Nicholas@guelph.ca

Phases

Phases overview
Information Sessions
Review
Phase one construction
Ask us anything!
Phase two construction
Phase three construction

Phase three construction

April 1, 2027 - December 31, 2027

During phase three, construction will be taking place from Janefield to Edinburgh and Gordon to Dundas Lane.