About the study
We have conducted a study in the Exhibition Park neighbourhood to enhance the park's infrastructure to manage flooding, upgrade aging systems and address ongoing challenges we have heard about from the community.
We have developed recommendations to address some of the infrastructure needs while planning for long-term sustainable development and efficiencies. The study looks at upgrades to sanitary sewers, watermains, stormwater sewers, and surface works identified in the Water and Wastewater Servicing Master Plan, the Stormwater Management Master Plan, and through asset management planning.
This included collecting field information (i.e. a topographic survey and soil information), evaluating design alternatives, and developing preliminary designs to inform detailed design and construction.

Study Area
Please note: This project began in an older version of our website. Some of the tools and information may appear different than originally designed.

Who's Listening

Colleen Gammie , Infrastructure Planning Engineer

Phases
Results
The study is complete and has recommended a program of works in the Exhibition Park Neighbourhood Area that will be undertaken in several detailed design and construction phases, as shown in the map below. The timing of each phase will be set and confirmed annually through the capital budget. These projects will be communicated to the neighbourhood as they are scheduled to begin and further engagement, should it be required on any of the projects in the program of works, will be included in communications.

Upcoming and ongoing events
Past events
Event date: February 11th, 2025 from 6:30 PM to 8:00 PM.
Victory Public School
Event date: October 8th, 2024 from 4:00 PM to 6:00 PM.
Guelph City Hall
Event date: June 24th, 2024 from 4:00 PM to 6:00 PM.
70 Division Street