University Avenue West Reconstruction
The City of Guelph will be proceeding with the reconstruction of University Avenue West (from College Avenue to Gordon Street). Reconstruction will include the replacement of underground utilities and surface works including sanitary sewers, storm sewers, watermains, services to property line, asphalt, curbs, sidewalks and other miscellaneous works.
The project is needed to replace underground infrastructure at the end of its service life, enhance accessible travel by replacing existing sidewalk with wider sidewalk and infilling the new sidewalk, and to address drainage challenges and better align to with the City’s Master plans.
How can I participate right now?
Attend the drop-in open house on February 11, 2026 from 6:30 - 8:30 at John McCrae Public School.
Let us know if you have any questions or concerns about this project by emailing Steve Huckabone (steve.huckabone@guelph.ca) or posting your question to Have Your Say for a member of the project team to respond to.
Map and Phasing of Construction Area:

Phases
Stage 2 Construction – Caledonia Street to Gordon Street
During this phase, construction from Caledonia Street to Gordon Street will take place. Construction for the second phase is expected to end late Fall 2027.
Construction notices will be distributed to impacted residences at least 2 weeks in advance of the contractor mobilizing that will provide the contractor and City project team’s contact information.
During construction residents can share any concerns with the project contact (Steve.Huckabone@guelph.ca) or through the Q and A tool.
Upcoming and ongoing events
Past events

Event date: January 21st, 2026 from 6:30 PM to 8:30 PM.
John McCrae Public School