York Road construction phase four

About the project

This is the fourth and final phase of the York Road Reconstruction project. In this final phase we are reconstructing York Road, from Victoria Road South the eastern city boundary this includes replacing aging sewer and water pipes and making necessary improvement to the road.

Phase four is further divided into the following stages:

  • Stage 1 - Watson Parkway to the east city limit (2025)
  • Stage 2: Victoria Road South to Industrial Place/ North Side of Watson Road (2027)
  • Stage 3 - Industrial Place to Watson Parkway (2028)

These dates are the City’s current estimate of when construction will be completed given the status of the individual projects. As with any construction project this schedule can be affected by contractor schedules, weather and any unforeseen issues that are sometimes encountered during construction.

Please note these dates may change as new information becomes available.

York Road Reconstruction Stages Map

A map of the sections of York Road that will be under construction for each stage. Stage 1 outlines Watson Parkway to the east city limit, stage 2 outlines Victoria Road South to Industrial Street, and Stage 3 outlines Industrial Street to Watson Parkway

Scope of reconstruction

The reconstruction of York Road in Stage 1 involves the following work:

  • Installation of curb and gutter between Watson Parkway and Watson Road;
  • Intersection improvements, including the addition or expansion of turning lanes;
  • Replacement of driveway aprons;
  • Installation of a storm sewer and stormwater management infrastructure, such as infiltration ponds in the boulevard;
  • Improving the existing sanitary sewer, with some replacements of existing sanitary maintenance holes and service connections;
  • New watermains; and,
  • Boulevard landscaping.

Full information about the project, the timelines, impacts and our strategies to mitigate those impacts is available in this information package.

How to participate

Thank you for attending the in person open house on April 15, 2025. If you missed the open house the materials from the open house are available for you to review including the information package and the project display boards. If you have any questions please contact the project manager, Pacifique Nicholas.

Please note: This project began in an older version of our website. Some of the tools and information may appear different than originally designed.

Phases

Phases overview
Information Period
Stage 1: Watson Parkway to east city limit
Stage 2: Victoria Road South to Industrial Place/ North Side of Watson Road
Stage 3: Industrial Place to Watson Parkway

Information Period

April 1, 2025 - May 11, 2025

An open house took place on April 15, 2025. The open house boards as well as an information package are attached below.

0 questions

No results found. Please try a different filter or search term.

Filters

Total posts: 0
There are no projects available.

Sorting changed to: Trending

No values available.

Selected zero tag filters.

Upcoming and ongoing events

    0 events have loaded.
    No upcoming or ongoing events are currently scheduled.

    Past events

    1 event has loaded.