York Road construction phase four

Share York Road construction phase four on Facebook Share York Road construction phase four on Twitter Share York Road construction phase four on Linkedin Email York Road construction phase four link

About the project

This is the fourth and final phase of the York Road Reconstruction project. In this final phase we are reconstructing York Road, from Victoria Road South the eastern city boundary this includes replacing aging sewer and water pipes and making necessary improvement to the road.

Phase four is further divided into three stages:

  • Stage 1 - Watson Parkway to the east city limit (2025)
  • Stage 2 - Victoria Road South to Industrial Street (2026/2027)
  • Stage 3 - Industrial Street to Watson Parkway (2028)

Stage 1 is expected to begin in May 2025 and to complete in November 2025 with the final road surface paving to happen in the spring of 2026. As with any construction project this schedule can be affected by contractor schedules, weather and any unforeseen issues that are sometimes encountered during construction.

Scope of reconstruction

The reconstruction of York Road in Stage 1 involves the following work:

  • Installation of curb and gutter between Watson Parkway and Watson Road;
  • Intersection improvements, including the addition or expansion of turning lanes;
  • Replacement of driveway aprons;
  • Installation of a storm sewer and stormwater management infrastructure, such as infiltration ponds in the boulevard;
  • Improving the existing sanitary sewer, with some replacements of existing sanitary maintenance holes and service connections;
  • New watermains; and,
  • Boulevard landscaping.

Full information about the project, the timelines, impacts and our strategies to mitigate those impacts is available in this information package.

How to Participate

Thank you for attending the in person open house on April 15, 2025. If you missed the open house the materials from the open house are available for you to review including the information package and the project display boards. If you have any questions please contact the project manager listed below.

Contact information

Should you have any further questions please contact:

Brennan Walker, Project Manager

Engineering and Transportation Services

City of Guelph

1 Carden Street, Guelph, ON N1H 3A1

519-822-1260 extension 2530

Brennan.Walker@guelph.ca

About the project

This is the fourth and final phase of the York Road Reconstruction project. In this final phase we are reconstructing York Road, from Victoria Road South the eastern city boundary this includes replacing aging sewer and water pipes and making necessary improvement to the road.

Phase four is further divided into three stages:

  • Stage 1 - Watson Parkway to the east city limit (2025)
  • Stage 2 - Victoria Road South to Industrial Street (2026/2027)
  • Stage 3 - Industrial Street to Watson Parkway (2028)

Stage 1 is expected to begin in May 2025 and to complete in November 2025 with the final road surface paving to happen in the spring of 2026. As with any construction project this schedule can be affected by contractor schedules, weather and any unforeseen issues that are sometimes encountered during construction.

Scope of reconstruction

The reconstruction of York Road in Stage 1 involves the following work:

  • Installation of curb and gutter between Watson Parkway and Watson Road;
  • Intersection improvements, including the addition or expansion of turning lanes;
  • Replacement of driveway aprons;
  • Installation of a storm sewer and stormwater management infrastructure, such as infiltration ponds in the boulevard;
  • Improving the existing sanitary sewer, with some replacements of existing sanitary maintenance holes and service connections;
  • New watermains; and,
  • Boulevard landscaping.

Full information about the project, the timelines, impacts and our strategies to mitigate those impacts is available in this information package.

How to Participate

Thank you for attending the in person open house on April 15, 2025. If you missed the open house the materials from the open house are available for you to review including the information package and the project display boards. If you have any questions please contact the project manager listed below.

Contact information

Should you have any further questions please contact:

Brennan Walker, Project Manager

Engineering and Transportation Services

City of Guelph